NASA says COVID-19 caused $3bn of delays to space missions

skynews

text

Delays caused by the coronavirus pandemic have cost NASA almost $3bn since last March, a report says.

COVID

-caused facility closures, mandatory remote working and disruptions to the materials supply chain have caused an enormous headache for **NASA

** , according to the space agency's office of inspector general (OIG) audit report.

It follows a previous

report into NASA's Artemis Programme

which warned NASA's plans to land the first woman and the next man on the moon by 2024 are "unlikely" to be achieved.

Please use Chrome browser for a more accessible video player

NASA releases footage of Mars landing

There are some upsides in the report, including NASA successfully landing its

Perseverance rover

on Mars.

It also found only minimal impact from the

coronavirus

pandemic on NASA's commercial crew programme, in which private companies like **SpaceX

**provide the agency with a domestic capability to launch astronauts into space.

Last May, during the first wave of the pandemic, NASA and SpaceX

successfully launched astronauts from US soil

for the first time in almost a decade.

However, despite these successes, a large number of important projects experienced moderate to significant impact from the pandemic, including NASA's double asteroid redirection test, and its new James Webb Space Telescope (JWST).

The JWST is an orbiting infrared observatory that will provide next-generation discoveries based on the work of the Hubble Space Telescope.

NASA's new Space Launch System, intended to design the massive super-heavy lift rocket that can propel humans to the moon again and perhaps even further on to Mars, also experienced significant set-backs.

The report reveals the challenges facing

President Biden's pick for NASA administrator,

the former space shuttle payload specialist Bill Nelson.

Alongside the astronaut landings, NASA had intended to establish a "Lunar Gateway" outpost which will be orbiting the moon by the mid-2020s, and then lunar landers to deliver cargo to the surface by the late 2020s.

The OIG report stated that due to numerous challenges facing the Lunar Gateway mission, "we anticipate further schedule delays and cost increases, making the Gateway unlikely to be available for the planned 2024 lunar landing".

It is not clear whether these missions will continue at all or if they will postponed.